Wednesday, 29 October 2008

UP-DATE - WORK IN PROGRESS











Today is a "day off" from the builders and their hard work.



This is because the back bedroom has now had all the plastering completed - including the ceiling and needs to dry out fully so that coving can be added. This will take place in a couple of days - on Friday
The windows have been ordered but will not arriive until 3rd November - bit if a pane (!) Still after that re-decorating can begin and the work move on.




Furthermore, the front lounge had all its plaster removed yesterday and the Damp Proof materials were injected. This stuff has to be left to soak in for two weeks before any re-plastering can take place in that room.


There will be some pauses whilst all these things are taking place.

Meantime, photos of work to date will be added as we go along to show you the progress ...